Our Current Projects

After a slow start to the year, 2009 is shaping out to be one of our most successful years despite the down economy.  The City of Springfield awarded us five out of six contracts to replace their aging sewer line.

 

Past Project

City of Newport, OR.

Sewer Line Replacement

Phase 2 of job three years ago

1,600 Lf from 10" to 14" (4 pulls)

May 2010

 

Prime:

WW Construction

 

Sub-prime:

UCMC / TTS

 

City of Portland, OR.

Sewer Line Replacement

259 Lf from 8" to 12"

521 Lf from 15" to 18"

January / April 2010

 

Prime:

Westech Construction

 

Sub-prime:

UCMC / TTS

 

City of Springfield, OR.

Sewer Line Replacement

30,000 L

8" Pipe Replacement and some line 15"-16"

May - January 2010

 

Prime:

H & J Construction

Harold Primrose Excavating/Eugene Sand & Gravel

Emery & Sons Construction

(5 contracts)

 

Sub-prime: UCMC / TTS

 

City of Hillsboro, OR.

2,900 Lf 10" to 14" and 10" to 16" Main Line

3,800 Lf of 4" - 4" Lateral Replacement

September - December 2009

 

Prime:  Excel Excavation, Inc.

Sub-prime:  UCMC / TTS

We were able to save a valuable tree

City of Beaverton, OR.

9,500 Lf of 4" and 6" / 169 Side Services

2,500 Lf 8" to 10" Main Line

August - October 2009

 

Prime:  Dunn Construction

Sub-prime:  UCMC / TTS

 

 

City of Gresham, OR.

2,000 Lf of 8" Main Line

September - October 2009

 

Prime:  Excel Excavation, Inc.

Sub-prime:  UCMC / TTS

Georgia-Pacific

Newport, OR.

Sliplining of 3,300 Lf ocean outfall for a Georgia-Pacific paper mill

18" as slipliner and installed through a 30" HDPE to get above the high tide

and pulled in place with a set of excavators and offshore tugboat, with divers

removing the defuser in 60' of water.  Special hydraulic head was fabricated for this project.

August 2007

 

Prime:   Kerr Contractors, Woodburn, OR.

Sub-prime:  UCMC / TTS

The photo gallery requires at least Flash version 9.0.28.

City of Toppenish, WA.

32,000 Total Lf of 8", 10", 12", 16", and 22"

740 side service saddles installed

Completed in 6 weeks.  Averaged 1,000 Lf / day

9,000 Lf 8" in 2003

23,000 Lf 10" - 22" in 2004

 

Prime:  T&G Construction

Sub-prime:  UCMC / TTS

Mt. Rainier National Park

Replaced 3,200 Lf of 6" water line for Paradise Lodge

Only dug up 45' total to install the pipe

1994

 

Prime:  Pipebusters

Sub-prime:  UCMC / TTS